Project Timeline
*All dates estimated based on supply chain and weather conditions.

July 2021………………. Excavation began

 

Aug. 2021……………… Construction of footers & foundation to begin

 

March 2022…………… Steel structure to be completed

 

Dec. 2022……………… Construction estimated to be completed

       Court personnel from 1969 Courthouse relocated to new building

 

Jan. 2023………………. Renovation of 1841 Courthouse begins

       Domestic Relations Court to be temporarily relocated to 1969 Courthouse

 

June 2023……………… Completion of 1841 Courthouse renovation

       Domestic Relations Court to be returned to renovated space