Latest News
12/20/22 – Public Officials’ Reception • Ribbon Cutting Ceremony • Open House
8/3/22 – Interior Progress Views
5/16/22 – Courthouse construction walk-through and rooftop views
4/18/22 – Outer light steel walls continue to go up around building
4/7/22 – Outer light steel walls going up; all concrete floors have been poured
3/16/22 – Concrete Floors Being Poured
3/15/22 – Topping Out Ceremony
2/23/22 – Steel being erected in sequences 4 & 5
2/10/22 – Steel continues to be erected in sequence 3
1/25/22 – Steel structure continues to go up. Steel progress is currently in Phase 2 out of 4 phases
1/14/22 – Steel arrived earlier in the week; Portion of steel structure started going up
1/7/22 – Large crane has arrived onsite in preparation for next week’s arrival of steel!
12/20/21 – Brick facade at top of east staircase has started going up
11/30/21 – Putting stairs in south staircase; Pouring north concrete; Finishing east staircase
11/23/21 – Continuing work on final staircase; progression on outer walls
11/15/21 – Concrete poured and cured; Working on final staircase
11/8/21 – Concrete walls are going up; Floor being poured
10/25/21 – Starting north staircase
10/19/21 – Working on underground utilities; Stacking south elevator; Starting south staircase
10/12/21 – Construction crews to continue work on staircases and elevator shafts
10/4/21 – Construction crews to continue work on staircases and elevator shafts
9/20/21 – Concrete blocks going up in stairwells and elevator shafts
9/13/21 – Electrical transmission box in place. Continuing work on underground plumbing
9/7/21 – Continuing to finish footers and starting underground plumbing
8/30/21 – Finishing foundation footers and hooking up to sanitary plumbing
8/23/21 – Storm water lines and footers
8/16/21 – Pads for Elevator Shafts Poured
7/15/21 – Groundbreaking Ceremony
7/12/21 – Excavation Progress Continues
7/7/21 – Demolition & Excavation underway
6/21/21 – Courthouse Entrance Changed